The Change Authorisation module is used to create and manage change authorisations. It can be used to print a Change Authorisation request ready for the signature of the Client and/or Project Manager and to record details of the change.
Figure 1.1 - Change Authorisation Register
To create a new change authorisation you can select the New button at the top of the form and open the Change Authorisation form.
Complete the necessary fields.
Figure 1.2 - New Change Authorisation
File Reference
Select the file reference you want to use for the change authorisation.
Originator
This is the originator of the change request.
Authorisation/Change No.
Enter the reference number of the change request. Some organisations may have their own numbering system that you may wish to reference. The number can be any combination of characters.
Re
Enter the part of the project that the change request refers to. Anything entered here will become selectable for future entries.
Rate raised
Enter the date that the change request was raised.
Date approved
Enter the date that the change request was approved.
Requested By
Enter the name of the person requesting the change.
Subject
Enter a brief description of the subject of the change request.
Description of Change
When using the Change Authorisation form to enter the data you can enter a description of the requested change.
Latest Date for Authority to Proceed
Enter the date that the change authorisation is required by.
Costs
- Enter the following costs resulting from the change in the relevant boxes provided.
- Basic Construction Cost
- Additional Preliminaries/Acceleration costs
- Professional Fees
- Sundry Costs
- Total cost of change
Net Effect of Proposed Change
Enter here the effect on the contract (e.g. delays, change in completion date) caused by the change.
Anticipated Contract Completion Date
Enter the anticipated date that the job will be finished.
Signatures
Enter the names of the Client and/or the Project Manager who signed the Change Request.
Distribution
Select the names of the people (from the project distribution list) who should be issued with copies of the Change Authorisation.
Date received
Enter the date that the change request was received.
Notes
Enter any notes you wish to record about the change request.
Printing the Change Authorisation
Select the Print button on the Change Authorisation form to print the Change Authorisation
Figure 1.3 - Change Authorisation Report